Project Status
Relocation of the water main, sewer main, and electric conduit off the existing 5th Street Bridge. This work is being done in advance of the City of New Smyrna Beach 5th Street Bridge replacement project.
Project Update
The water and wastewater work has been completed. The electric work has begun and will continue for the next 4 weeks. NSBU utility work and restoration efforts will be completed by end of March 2023.
Project Contacts
Project Manager: Dana Hale P.E.
Contractor: Y-COM/ K3 Drilling