Skip to main content

Projects Update

  • Lift Station 5 Reconstruction

    This project will replace the existing sanitary sewer lift station and associated force main work on Beacon Street between Inlet Street and Tide Street. The force main work is complete. The contractor will mobilize and start installation of new wetwell. 

    Start Date
    Completion Date
    Project Contacts

    Dana Hale, P.E. for NSBU

    Hazen Construction, contractor

  • Pioneer Trail Reconductoring

    NSBU and our contractor, Pike, is rebuilding the overhead electrical line along Pioneer Trail between roughly Williamson Blvd to the I-95 overpass. The project will require MOT/lane closure for the majority of the work. Construction is underway.

    Start Date
    Completion Date
    Project Contacts

    Kory Sandven, NSBU Electrical Engineer, 386-424-3060

     

  • GWTP Chemical Upgrades

    Chemical conversion from gas to liquid treatment.

    Project Update

    Preliminary project work such as processing of long lead equipment submittals and relocation of gopher tortoises have been completed. Site work has begun for new chemical buildings. 

    Project Contacts

    Project Manager: Darren Phegley, P.E.

    Contractor: Odyssey Manufacturing Company

  • Potable Water Well Rehabilitation Plan

    A 5-year potable water well rehabilitation plan for 19 wells. This maintenance and rehabilitation plan will optimize the production of our wells and ensure the safeguarding of our precious water resource.

    Project Update

    We are currently working in the Western Wellfield where work on Wells #15, #16, and #17 has been completed. We are currently working on Wells #19 and #20.

    Project Contacts

    Project Manager: Darren Phegley

    Contractor: AC Shultes of Florida, Inc.

  • Lift Station 12 Replacement Project

    This is for the reconstruction of the existing lift station located at the NW corner of Duss Street and Washington Street, which will include new discharge piping between Mary Avenue and Washington Street.

    Project Update

    Lift Station work continues. Work is estimated to be complete in June 2023.

    Project Contacts

    Project Manager: Dana Hale P.E.

    Contractor: Carr & Collier, Inc.

  • Barracuda Bridge Utility Replacement Project

    Barracuda Bridge

    All water main work has been completed. The first two phases have been cleared by the Department of Health. NSBU Field Operations has begun connecting new water services in these two phases. The last phase is currently being tested. Once cleared for use, the final water main connection can be scheduled. The final apshalt patch work is scheduled for the week of May 8th. NSBU and the City are working together on a final paving restoration plan and schedule.

     

    Project Update

    The water main work continues in the Venezia neighborhood. 

    Project Contacts

    UC Project Manager:  Dana Hale

    Contractor: Y-COM

  • Annual Gravity Sanitary Sewer Rehabilitation Project

    Annual, ongoing project, projected to continue through 2024
    Project Update

    Crews are working in System 73 in the Sugar Mill neighborhood.

    Project Contacts

    UC Project Manager:  Dana Hale

    Contractor: BLD Services, LLC/LMR Construction, Inc.

  • Glencoe Well Rehab

    Rehabilitation of Glencoe Well Sites No. 2 and No. 3

    Project Update

    Long lead time for equipment continues to delay completion of the project. We estimate that crews will complete instrumentation and control items, finish remaining site work, and complete demotion of existing well houses early this summer. 

    Start Date
    Project Contacts

    UC Project Manager: Darren Phegley

    Contractor: McMahan Construction Co., Inc.