Skip to main content

Projects Update

  • Lift Station 12 Replacement Project

    ​​​​​​​Carr & Collier, Inc. has been contracted to reconstruct the existing lift station located at the NW corner of Duss Street and  Washington Street, which will include new discharge piping between Mary Avenue and Washington Street.  The pipe work will commence October 24, 2022.  The lift station work will begin January 2023.  This project is expected to be completed in June 2023.

    Start Date
    Completion Date
  • 5th Street Bridge Utility Replacement Project

    Y-COM and their sub-contractor K3 Drilling has been contracted to relocate the water main, sewer main, and electric conduit off the existing 5th Street Bridge. This work is being done in advance of the 5th Street Bridge replacement project.  The drilling will begin October 24, 2022 and continue for 6 weeks.

    Start Date
    Completion Date
  • Barracuda Bridge Utility Replacement Project

    Barracuda Bridge

    UC Project Manager:  Dana Hale

    Contractor: Y-COM

    Start Date: December 2021

    Projected Completion: August 2022

    Project Area: Work extends along Quay Assisi, North Causeway and South Riverside Drive

    Start Date
    Project Contacts

    UC Project Manager:  Dana Hale

    Contractor: Y-COM

  • Annual Gravity Sanitary Sewer Rehabilitation Project

    Projected Start/Completion Date: Annual, ongoing project, projected to continue until 2024

    Start Date
    Project Contacts

    UC Project Manager:  Dana Hale

    Contractor: BLD Services, LLC/LMR Construction, Inc.

  • Glencoe Well Rehab

    Project Name: Rehabilitation of Glencoe Well Sites No. 2 and No. 3

    Projected Completion: February 2023

    Start Date
    Project Contacts

    UC Project Manager: Darren Phegley

    Contractor: McMahan Construction Co., Inc.